BOILER
4 & 5
Cleaver Brooks High Pressure Boilers
Contract Amount
$5 MM
Duration
24 Months
Contract Type
Lump Sum
Location
Casa Grande, AZ
Market
Industrial
Owner
Abbott Nutrition
General Contractor
Sun Mechanical
Architect
HDR
Engineer
HDR
Market
Industrial
Owner
Abbott Nutrition
General Contractor
Sun Mechanical
Architect
HDR
Engineer
HDR
Project Description
Sun Mechanical was the general contractor for the complete demolition and complete installation of (2) new Cleaver Brooks High Pressure Boilers that are roughly sized at 30’ x 15’ x 15’. This capital improvement project required multiple different divisions of scopes including soil inspection/testing, demolition, helical piles, concrete, structural steel, roofing, plumbing, process piping, heavy equipment installation, HVAC,
insulation, electrical, and painting. Sun mechanical provided all in-house divisions as well as subcontractors needed to complete this project in the provided schedule to the owner.